Actualidad Info Actualidad

Sustainable planning & unknown users: A challenge for research facilities design process

Michael Scheuern, University of Luxembourg, L-1511 Luxembourg, Luxembourg11/12/2012
The University of Luxembourg, founded in 2003 will get new building premises on the former industrial site 'Belval', located in the south of the Grand Duchy of Luxembourg. On a surface of 15,48 hectares in a first phase, 8 buildings will form the 'Cité des Sciences' with overall 170.000 sqm (gross) for 1.800 researchers and 7.000 students. The investment for the construction exceeds 850.000.000 , to which is added the part scientific equipment for about 300.000.000 .

Sustainability is one of the objectives, which has driven the Luxembourgish government to make this decision.

A focus will be given on laboratory buildings, even to develop the smart ongoing research in this domain in appropriate facilities. For 2016 12.500 sqm laboratory buildings will be ready to accommodate mainly researchers for bio-medicine and material sciences topics. The project management team is in the special situation, that there are no former researchers who can give input. The development of space programs has to be done simultaneously with the definition, the growth and the recruitment of professors. Given the long construction period, especially when money comes from the public sector, the flexibility of the building plays a key role in this concept and offers advantages in sustainability by long-term using.

In a building design process, the required pieces of information are wide spread, and normally you will not start the construction until you have defined all the details, the technics of the building and the interior fittings included. This is required to follow budget and also time frame. To do this, you need normally the whole users’ input in a very early moment.

A strong analysis of the time schedule of this input for the design process had been done, and showed an analogy of the life cycle of the different lots as structures and building shells, building equipment, interior fittings and furniture. We gathered all the pieces of information for each lot and defined groups with early, less early and later information requirements.

As it has not always been possible to collect exact physical data (like floor charges, ventilation air rate, …), we reversed in those cases the process by defining ranges of exclusion data, then the summation of those data enables to describe the global performance of the building and gives the frame for the flexible use.

We had the great opportunity to build up a 2.000 sqm laboratory building, where we used this planning method. We were able to deliver a functional lab building after a construction period of 18 months. After one year of use, we have the proof that flexibility has been respected and the performance of the building does not show any shortcoming.

The project team needs a strong discipline to respect the continuity and the link of the different project phases. A lot of communication was necessary to explain this concept to researchers and the contractual partners as the consulting engineers and suppliers.

I am personally convinced that this planning method matches perfectly with advanced construction economy models as general enterprise models, built operate transfer models (BOT), and it is also a solution for dealing with the design process in the case of building lease.

Suscríbase a nuestra Newsletter - Ver ejemplo

Contraseña

Marcar todos

Autorizo el envío de newsletters y avisos informativos personalizados de interempresas.net

Autorizo el envío de comunicaciones de terceros vía interempresas.net

He leído y acepto el Aviso Legal y la Política de Protección de Datos

Responsable: Interempresas Media, S.L.U. Finalidades: Suscripción a nuestra(s) newsletter(s). Gestión de cuenta de usuario. Envío de emails relacionados con la misma o relativos a intereses similares o asociados.Conservación: mientras dure la relación con Ud., o mientras sea necesario para llevar a cabo las finalidades especificadasCesión: Los datos pueden cederse a otras empresas del grupo por motivos de gestión interna.Derechos: Acceso, rectificación, oposición, supresión, portabilidad, limitación del tratatamiento y decisiones automatizadas: contacte con nuestro DPD. Si considera que el tratamiento no se ajusta a la normativa vigente, puede presentar reclamación ante la AEPD. Más información: Política de Protección de Datos

REVISTAS

VÍDEOS DESTACADOS

  • Guía de instalación y mantenimiento de Discos de Ruptura

    Guía de instalación y mantenimiento de Discos de Ruptura

TOP PRODUCTS

NEWSLETTERS

  • Newsletter Farmacia

    12/11/2024

  • Newsletter Farmacia

    29/10/2024

ENLACES DESTACADOS

Net Zero Tech 2025Sick Optic-Electronic, S.A.U

ÚLTIMAS NOTICIAS

EMPRESAS DESTACADAS

OPINIÓN

OTRAS SECCIONES

SERVICIOS