This news article was originally written in Spanish. It has been automatically translated for your convenience. Reasonable efforts have been made to provide an accurate translation, however, no automated translation is perfect nor is it intended to replace a human translator. The original article in Spanish can be viewed at Colapso total en la cogeneración por el retraso de los pagos de la CNMC

I collapse total in the cogeneration by the delay of the payments of the CNMC

28/03/2014

28 March 2014

In 2013, the 970 installations of cogeneration (generadoras of the electricity and the steam that require the industries that manufacture 20% of the industrial production of Spain in feeding, chemical, papeleras, azulejeras…), perceived 2.912 millions by the sale of his electricity (12% of the national electricity), that is to say 350 millions less than in 2012. Besides, new taxles and cuts arisen also of the reform, imposed him 650 millions more than loads.

These companies credit annually by the gas that require to realizar his production (25% of the national total consumption) 3.000 million euros, that suppose until 80% of his costs of manufacture.

Does a month, the Government presented his proposal of reward elevating the annual impact to the cogeneration until more than 1.000 annual millions (32% of the income), leaving to the sector in operative losses. The announcement drove to that it stopped gradually until 40% of the sector to avoid greater losses.

Now, the CNMC, following the regulation of the Government, delays the payments of the available bills of electricity to the cogeneradores, making impossible that these face up to the payment of his suppliers, mainly of fuels (natural gas, fuel, biomass...), planting like this to the sector to the doors of a collapse total that will drag to the industrial production and to the employment associated.

Plant of cogeneration
Plant of cogeneration.

The only entry received by the electricity sold in what it goes of year, has been only the fourth part of his reward of January. The CNMC communicated on 14 March that applied súbitamente a coefficient of coverage of only 25,5% to the pending settlements of the month. That is to say, of the part that credits the CNMC to the cogeneration by the electricity sold to the system, in January only has earned 25% (now, after 45 days of prescriptive term). The sector does not know when will pay him the CNMC the remaining 75%, something that according to the legal terms can lengthen months or even years. For a cogenerador, that has to pay all the months the bills of gas with which manufactures electricity and heat for his use in the industrial production, this situation causes vital tensions in the tesorería of his industry and of his plant of cogeneration.

The CNMC communicated, in presses release the past 18 March: “With the aim to reduce the impact that has this normative change on the financial situation of the agents involved, with this settlement the CNMC will send to all they a certificate where recognises the quantity devengada by each one of the subjects of the system of settlements. Of this way, attends the request effected by the organisations of renewable energies, cogeneration and waste treatment, that demanded a supporting document of the whole of the defeated payments of the period (quantity devengada) to minimise the impact of the normative change.”

In spite of this communication, the CNMC says now that they do not have foreseen to issue any type of certificate, that only accompany the bill with an estadillo where reflects 100% of the settlement. This estadillo does not serve to the companies to accredit or guarantee the pending debt of the CNMC.

The CNMC fulfils like this with the regulation that promulgó the Government for the economic stability of the electrical system and that now demands to the industries cogeneradoras that fund unfit them of the electrical system.

But the problem with the payments of January, far to remit seems that it will keep in the next months. For the settlements of February, is predictable -of agreement to the historical of other years, since it has not communicated at all officially-, that the payments of the CNMC keep on being minors of 50% of the bills, covering progressively greater heights for the summer and final of year, pending all this of how go the income and electrical costs regulated. The financial directors of the cogenerations and industries associated afanan in posing stages without official information neither of the quantities to pay neither by how long.

The tension is maximum in companies that have received warnings of his providers of fuels announcing that if they do not proceed to the payment will cut immediately the supplies, given the total uncertainty and delays in the energetic reform. The industrial companies and his cogenerations are looking for the support of his societies matrices, banks, trading companies of gas, etc. Without supply of fuels will not be able to follow cogenerado and/or manufacturing.

The trading companies of gas/providers of fuel share his worry with the industries in what numerous companies associated to Receive have defined like moment of maximum tension with enormous difficulties to attend the payments of supplies, personal and operations, in front of the non-payments that is moving the CNMC in accordance with the regulated by the Government.

The situation is of total uncertainty with an increasing number (until 40%) of unemployed plants: in March the production of electricity in cogeneration has gone down 35% (REE) in front of the same month of 2013.

For Javier Rodríguez, general director of Receive, “is incredible that have not foreseen the grave damages to which abocan these non-payments of the Government, without promoting measure any to mitigate them or manage them. If somebody thinks that the industry manufacturera can fund to the electrical system is that desconoce the situation of the real economy: after more than six years of crisis struggling for producing, export and keep the employment, these non-payments suppose the puntilla final for a lot of companies”.

Related Companies or Entities

Asociación Española de Cogeneración

Suscríbase a nuestra Newsletter - Ver ejemplo

Password

Select all

Autorizo el envío de newsletters y avisos informativos personalizados de interempresas.net

I authorize the sending of communications from third parties via interempresas.net

He leído y acepto el Legal notice y la Data protection policy

Responsable: Interempresas Media, S.L.U. Purpose: Subscription to our newsletter(s). User account management. Sending emails related to the same or related to similar or associated interests.Retention: for the duration of the relationship with you, or as long as necessary to carry out the specified purposesTransfer: Data may be transferred to other group companies for internal management purposes.Rights: Access, rectification, opposition, deletion, portability, limitation of processing and automated decisions: contact our DPD. If you consider that the processing does not comply with the regulations in force, you may lodge a complaint with the AEPD.More information: Data protection policy

REVISTAS

VÍDEOS DESTACADOS

  • Construcción de balcones: cerámica con sistema de drenaje, impermeabilización y desolidarización.

    Construcción de balcones: cerámica con sistema de drenaje, impermeabilización y desolidarización.

  • Electro portátiles 18V

    Electro portátiles 18V

TOP PRODUCTS

NEWSLETTERS

  • Newsletter Arquitectura y Construcción

    04/07/2024

  • Newsletter Arquitectura y Construcción

    02/07/2024

Highlighted links

Matelec - IFEMAAsociación Española de Fabricantes de Fachadas Ligeras y VentanasPiscinaSpainFeria de la Construcción (17 a 19 Octubre 2024)Asefave27&28 Noviembre IFEMA (Madrid)

Latest news

Featured companies

OPINIÓN

ENTIDADES COLABORADORAS

OTRAS SECCIONES

Services